Workshop and office electrical installation for SUEZ R&R UK Ltd. We were commissioned to design, install, test and commission the full electrical infrastructure for a new SUEZ workshop and office facility, taking the project from supply upgrade through to fire alarm, CCTV and fibre handover.
250A three-phase distribution

A new 250A three-phase supply was installed to serve the workshop, terminating into a new 250A panel board. From there, distribution feeds were run to boards serving the workshop and the new office block, giving the facility a robust distribution system matched to its operational load. Cable calculations covered sizing, protective-device selection, voltage drop and fault protection on every circuit.

Lighting and emergency lighting

We carried out a full lighting design covering general and emergency lighting across the facility. The install included high-level containment and electrical supplies for the lighting system, with emergency lighting integrated into the overall design to deliver appropriate illumination levels and full escape-route coverage.

Electrical containment

A substantial containment system was installed throughout the workshop and office areas, including 6″ × 6″ two-compartment trunking that keeps services properly segregated, plus high-level containment for the lighting and ventilation systems. The whole run was planned for a neat, accessible finish that supports future maintenance and alterations.

Fire alarm first and second fix

We delivered both first and second fix of the fire alarm, including all cabling and associated electrical work. The fire-alarm infrastructure was coordinated alongside the other electrical and building services for a fully integrated install.
CCTV, OM4 fibre and 110V workshop power

CCTV cameras were supplied and installed to cover the facility, with cabling and containment designed into the main install to avoid surface wiring. OM4 multimode fibre optic cable was supplied, installed and terminated to give the site a high-speed communications backbone. In the workshop we installed a dedicated 110V transformer and 110V socket outlets to power portable tools and equipment safely.
Roller-door and heating interlock

We installed door contacts on the workshop roller doors and integrated them with the heating controls. When a roller door is opened, the associated heating switches off automatically, cutting wasted energy and improving building efficiency.
Workshop extraction and MOT lane

High-level extraction reels were connected and commissioned above the vehicle bays, with power and controls coordinated with the MOT lane layout. Hazard striping and bay markings were coordinated with our containment runs so the finished floor reads cleanly from the shop-floor side.

Project result

The completed install gives SUEZ R&R UK a fully coordinated electrical and communications infrastructure covering 250A three-phase distribution, workshop and office boards, general and emergency lighting, fire alarm first and second fix, CCTV, OM4 fibre, 110V workshop power, heating and roller-door interlocking, high-level containment, two-compartment trunking and full cable calculations and electrical design.