16 October 2026 2 min read

Workshop and office electrical install for SUEZ R&R UK

Full electrical fit-out of a new SUEZ R&R UK workshop and office facility — 250A three-phase distribution, lighting and emergency lighting design, fire alarm first and second fix, CCTV, OM4 fibre, 110V workshop power and heating/roller-door interlocks, all delivered as a single coordinated install.

Talk to an engineer All articles
Finished SUEZ workshop overview — lighting, extraction and MOT lane layout Article

Workshop and office electrical installation for SUEZ R&R UK Ltd. We were commissioned to design, install, test and commission the full electrical infrastructure for a new SUEZ workshop and office facility, taking the project from supply upgrade through to fire alarm, CCTV and fibre handover.

250A three-phase distribution

250A distribution boards, sub-panels and sub-mains cabling
250A distribution boards, sub-panels and sub-mains cabling

A new 250A three-phase supply was installed to serve the workshop, terminating into a new 250A panel board. From there, distribution feeds were run to boards serving the workshop and the new office block, giving the facility a robust distribution system matched to its operational load. Cable calculations covered sizing, protective-device selection, voltage drop and fault protection on every circuit.

Wall-mounted 3-phase outlet station with isolator
Wall-mounted 3-phase outlet station with isolator

Lighting and emergency lighting

Workshop ceiling — lighting, extraction and PA cabling
Workshop ceiling — lighting, extraction and PA cabling

We carried out a full lighting design covering general and emergency lighting across the facility. The install included high-level containment and electrical supplies for the lighting system, with emergency lighting integrated into the overall design to deliver appropriate illumination levels and full escape-route coverage.

High-level lighting and extraction containment
High-level lighting and extraction containment

Electrical containment

High-level cable containment and sub-mains tray
High-level cable containment and sub-mains tray

A substantial containment system was installed throughout the workshop and office areas, including 6″ × 6″ two-compartment trunking that keeps services properly segregated, plus high-level containment for the lighting and ventilation systems. The whole run was planned for a neat, accessible finish that supports future maintenance and alterations.

Containment run feeding workshop outlet station
Containment run feeding workshop outlet station

Fire alarm first and second fix

Office corridor — LED panels, fire-alarm panel and call point
Office corridor — LED panels, fire-alarm panel and call point

We delivered both first and second fix of the fire alarm, including all cabling and associated electrical work. The fire-alarm infrastructure was coordinated alongside the other electrical and building services for a fully integrated install.

CCTV, OM4 fibre and 110V workshop power

110V transformer sockets and emergency stop pillar
110V transformer sockets and emergency stop pillar

CCTV cameras were supplied and installed to cover the facility, with cabling and containment designed into the main install to avoid surface wiring. OM4 multimode fibre optic cable was supplied, installed and terminated to give the site a high-speed communications backbone. In the workshop we installed a dedicated 110V transformer and 110V socket outlets to power portable tools and equipment safely.

Roller-door and heating interlock

Roller-door emergency stop and air services station
Roller-door emergency stop and air services station

We installed door contacts on the workshop roller doors and integrated them with the heating controls. When a roller door is opened, the associated heating switches off automatically, cutting wasted energy and improving building efficiency.

Workshop extraction and MOT lane

Ceiling-mounted extraction reel array
Ceiling-mounted extraction reel array

High-level extraction reels were connected and commissioned above the vehicle bays, with power and controls coordinated with the MOT lane layout. Hazard striping and bay markings were coordinated with our containment runs so the finished floor reads cleanly from the shop-floor side.

MOT pit with hazard striping and bay markings
MOT pit with hazard striping and bay markings

Project result

Workshop pit and MOT lane with yellow and black hazard striping
Workshop pit and MOT lane with yellow and black hazard striping

The completed install gives SUEZ R&R UK a fully coordinated electrical and communications infrastructure covering 250A three-phase distribution, workshop and office boards, general and emergency lighting, fire alarm first and second fix, CCTV, OM4 fibre, 110V workshop power, heating and roller-door interlocking, high-level containment, two-compartment trunking and full cable calculations and electrical design.